School construction project moving along

Maple Lake Public Schools HVAC construction project is on schedule with completion expected sometime in August. The pictures above show some of the progress being made. According to an update provided by Supt. Mike Rowe, 85 % of the lighting is installed at the elementary school as is 85 % of the grid; the rooftop and air handling units are 75 percent set; the media center ductwork is complete along with surrounding offices; duct cleaning in the elementary school is done and piping in the elementary school is 90 percent complete. In the coming weeks crews will work on installing ductwork in the elementary and district offices; installing structural steel in the district office, media center and high school mezzanine; pouring the chiller pad, sidewalk and housekeeping pad and setting the rest of the rooftop units.